| |
|
The UCLA Westwood Replacement Hospital will be the
dominant building of the south campus area. Designed by the
architect team of Perkins & Will, I.M. Pei, Architect, Pei
Partnership Architects, and RBB Architects, the building conveys
the inspiration and promise of healing and scientific discovery,
along with the openness, accessibility, and human scale inherent
on the UCLA campus
|
|
|
|
|
*NEW ADDITIONS!*
|
(as of June 2006)
|
Renders - March 2006
The photographic collection of the current progress versus the architect's images has been updated! SEE HERE
Chronology - March 2006
The photographic collection of the construction site has been updated! SEE BELOW
Schedule - March 2006
The Schedule - a timeline of the project has been updated! SCHEDULE
Archived Updates...
|
CURRENT PROJECT STATUS
|
(as of December 2006)
|
The Westwood Replacement Hospital team participated in their Annual Toy Drive with nearly 400 toys being donated to the UCLA Fire Department for distribution. This marked the 6th year the Project Team has participate in the program. Pictured above are some of those responsible for organizing the event.
Building Exterior Finishes & Sitework
Exterior wall panel installation and roofing installation has completed. Installation of the exterior doors remains. The Westwood Hospital has taken its finished shape and appearance with curved towers, rectilinear stone cladding, sunshades, balconies, upper courtyards, and glass window walls. Average daily manpower is near 400 workers.
Sitework is well underway with the recent completion and opening of the new intersection of CYD West and Gayley Ave. This will serve as the Children’s Hospital entrance, the Emergency Room entrance and access to patient pick-up and drop off area. The realignment of Gayley Ave is underway and anticipated to complete by the end of May. Construction of the South Plaza is progressing. Sitework at the main entrance off of Westwood Plaza is schedule to occur in the early summer. Activities include driveways, sidewalks, lighting and landscaping.
Interior Finishes
Interior finishes are progressing from the east side of the building toward the west. In the upper floors (4 through 8) of the Northeast, Southeast and Central Towers, drywall installation is complete with finish paint, ceramic tile, flooring, ceiling and door hardware installation nearing completion. Casework installation continues in the patient rooms and nurse station areas.
In lower floors of the building, work is primarily focused on completing inspection of overhead installations to be followed by installation of finish ceilings and remaining interior finishes. Mechanical systems are being brought on line with testing and flushing of plumbing systems. Complete functional systems are necessary in preparation for the start-up and final commissioning effort. Final Vendor data has been received and incorporated into the design to allow completion of Radiology areas.
The main entrance to the 1st Floor public spaces including main lobby and cafeteria areas are beginning to reflect their final appearance with the installation of Terrazzo flooring, custom wall panels and finish ceilings.
Mechanical Equipment and Elevators
Mechanical installation is nearing completion in the B2 Level basement, 3rd floor and roof penthouse areas. These activities include seismic bracing of mechanical and electrical equipment (i.e., air handlers, compressors, electrical switchgear and transformers, etc.), installing interconnecting piping, conduit and ductwork and testing of completed systems. Progress on the startup and testing of these systems is vital to completion of the building. Elevator cabs are in place and most elevator door fronts are installed.
|
INTERESTING SITE FACTS
|
(as of April 2006)
|
26,000 tons of structural steel
70,000 cubic yards of concrete
Footprint of the building = 4 acres
Over 1 million square feet of interior building area
25 Elevators
525 Beds
|
QUESTIONS & ANSWERS
|
(as of Dec 2003)
|
Where are Exterior Wall Panels made?
The exterior wall panels on the Westwood Hospital are custom made and assembled in Portland, Oregon. Components for the system are procured from vendors around the world. Stone cladding was quarried, cut and finished in Tivoli, Italy, glass is manufactured in Owatonna, Minnesota and aluminum extrusions and panels are manufactured in Seoul, Korea. A project of this complexity requires every aluminum extrusion to be custom designed.
Due to the Northridge Earthquake, the exterior wall panels are required to comply with the 1998 California Building Code. Critical performance standards of the code require that the exterior wall system be designed to withstand an earthquake of 8.4 Richter magnitude with no significant structural failure and no elements of the exterior cladding falling off the building. In addition, the building must remain operation after a major earthquake. Basic performance standards require the building to withstand winds of 70mph and driving rain conditions.
A full-scale mock-up of the system was built at a testing laboratory in Los Angeles to duplicate these conditions. The mock-up was subjected to these extreme conditions to verify its performance. Only after passing all water, wind and earthquake requirements was the system approved for fabrication and installation.
Email Questions and Comments To mcastaneda@ucmt.org

What's New On The Webpage
10/29/01 - Current News Update Design- A weekly review and look ahead at project information.
2/5/02 - Delivering The Promise - Informative video link located under the about menu.
1/5/04 - Photographic Collection Updated.
Some webpage files may require additional programs to open and view them. The links below will help you download the necessary plug-ins required.
|
|
|
|